We carried out a retrospective critical path delay analysis based on available documentation and supplemented missing data through structured interviews and corroborative evidence. Our report was designed to meet judicial standards, with clearly articulated methodology, findings, and conclusions aligned with best practices in forensic delay analysis.
Outcome
The experts appointed by the Court of Appeals adopted the conclusions presented in our delay report. Based on these findings, the Court of Appeals issued a revised ruling that reduced the award to the main contractor by 70%, representing a significant win for the
owner.
Our Role
We were appointed as delay experts to support the owner’s position during the appeal process. Our team conducted a comprehensive and objective delay analysis and produced an independent expert report.
This report was formally submitted to the Court of Appeals as part of the owner’s defense.

Litigation – Residential Building
This case involved a residential building project in Dubai, where the owner was the defendant in a litigation initiated by the main contractor. The Dubai Court of First Instance issued an unfavorable ruling against the owner, prompting an appeal to the Court of Appeals.
Key Challenges Navigated
01
The initial court ruling had already set a difficult precedent
02
Limited access to contemporaneous project records
03
Tight deadlines for preparing and submitting expert evidence within the appeal window
.png)
Check us out
Have any questions?
Please don’t hesitate to contact us
Phone: +971 4 252 2202
Mobile: +971 50 3590439
Email: info@paradvisory.com
Our Menu
Location
Court Tower Office 1902,
Marasi Drive, Business Bay
Dubai, United Arab Emirates
P.O.B: 127477